Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Bijnor
AGENCY LC INFRA
SCHEME ID 20018324
SCHEME NAME Jalpur Guddar Water Supply Scheme
ESTIMATED COST 472.47
EXPENDITURE 262.68
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 30
Procured 30 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 18042.00 Meter
Length Laid 18000.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bijnor Najibabad Jalabpur Gudal 385701 Arafpur Khajuri 40 40 100% Har Ghar Jal Not Certified
2 Bijnor Najibabad Jalabpur Gudal 385702 Jalpur Guddar 601 601 100% Har Ghar Jal Not Certified
3 Bijnor Najibabad Jalabpur Gudal 385703 Khushhalpur Marka 144 144 100% Har Ghar Jal Not Certified