Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Lucknow | NCC Ltd. | 20018707 | KUNAURA SHAHPUR | 328.60 | 190.80 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 21 | 21 | Yes | 0 | NA | No | 17840.00 | 17840.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lucknow | Bakshi-ka-talab | Kunaura | 415578 | Kunaura | 272 | 263 | 97 | Work In Progress | Not Certified |
| 2 | Lucknow | Bakshi-ka-talab | Kunaura | 415579 | Shahpur Najol | 133 | 124 | 93 | Work In Progress | Not Certified |
| 3 | Lucknow | Bakshi-ka-talab | Kunaura | 415580 | Lalpur | 130 | 124 | 95 | Work In Progress | Not Certified |