Scheme Details
DISTRICT Gonda
AGENCY Larsen & Toubro Ltd
SCHEME ID 20018825
SCHEME NAME Anegi Water Supply Scheme
ESTIMATED COST 244.79
EXPENDITURE 121.44
AUTOMATION STATUS
Disconnected View Live Screen
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 14
Procured 14 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 10205.00 Meter
Length Laid 6290.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Gonda Rupaidih Anagi 444625 Anagi 231 231 100% Har Ghar Jal Not Certified
2 Gonda Rupaidih Anagi 444626 Harryaban 55 36 65% Work In Progress Not Certified