Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bareilly | NCC Ltd. | 20019382 | BISHANPUR GULARIA & CHHITAUNIA Water Supply Scheme | 329.83 | 202.57 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 22 | 22 | Yes | 0 | NA | No | 17471.00 | 19180.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Baheri | Bishanpur Gularia | 402608 | Bishanpur Gularia | 103 | 103 | 100 | Har Gar Jal | Not Certified |
| 2 | Bareilly | Baheri | Bishanpur Gularia | 402609 | Patrasi | 90 | 90 | 100 | Har Gar Jal | Not Certified |
| 3 | Bareilly | Baheri | Bishanpur Gularia | 402610 | Aliganj | 90 | 90 | 100 | Har Gar Jal | Not Certified |
| 4 | Bareilly | Baheri | Chhitaunia | 402617 | Chhitaunia | 258 | 258 | 100 | Har Gar Jal | Not Certified |