Scheme Details
DISTRICT Farrukhabad
AGENCY GVPR
SCHEME ID 20019511
SCHEME NAME Ramapur Dabir W/S Scheme
ESTIMATED COST 193.15
EXPENDITURE 162.11
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 16
Procured 16 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 5467.00 Meter
Length Laid 6895.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Farrukhabad Nawabganj Ramapur Dabir 418082 Ramapur Dabir 341 341 100% Har Ghar Jal Not Certified
2 Farrukhabad Nawabganj Ramapur Dabir 655915 JAY SINGHPUR 10 10 100% Har Ghar Jal Not Certified