Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Sitapur | NCC Ltd. | 20019578 | Kutubapur | 309.60 | 119.61 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Sitapur | Pisawan | Kutuapur | 409609 | Dafrapur | 127 | 115 | 91 | Work In Progress | Not Certified | Not Verified |
2 | Sitapur | Pisawan | Kutuapur | 409610 | Himmat Nagar | 114 | 104 | 91 | Work In Progress | Not Certified | Not Verified |
3 | Sitapur | Pisawan | Kutuapur | 409611 | Kapur | 102 | 96 | 94 | Work In Progress | Not Certified | Not Verified |
4 | Sitapur | Pisawan | Kutuapur | 409612 | Katuapur | 216 | 195 | 90 | Work In Progress | Not Certified | Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 21 | 21 | Yes | 0 | NA | No | 13206.00 | 13206.00 |