| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | NCC Ltd. | 20019710 | Kuiyan kataiya | 239.56 | 160.40 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 19 | 19 | Yes | 0 | NA | No | 8240.00 | 8240.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | Kanth | KUIYAN KATAIYA | 407072 | HARIPUR | 88 | 86 | 98 | Work In Progress | Not Certified |
| 2 | Shahjahanpur | Kanth | KUIYAN KATAIYA | 407073 | KATAIYA ELAQAKUIYAN | 89 | 86 | 97 | Work In Progress | Not Certified |
| 3 | Shahjahanpur | Kanth | KUIYAN KATAIYA | 407074 | KUIYAN ELAQA KATAIYA | 150 | 150 | 100 | Har Gar Jal | Not Certified |
| 4 | Shahjahanpur | Kanth | KUIYAN KATAIYA | 407075 | BAHADURPUR | 80 | 80 | 100 | Har Gar Jal | Not Certified |