Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Bareilly | NCC Ltd. | 20019900 | Dandiya Nazmul NIsan & Saraura Water Supply Scheme | 308.51 | 189.33 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 19 | 19 | Yes | 0 | NA | No | 12505.00 | 12280.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Bhadpura | Surajpur Parauria | 403979 | Surajpur Parauria | 244 | 240 | 98 | Work In Progress | Not Certified | 
| 2 | Bareilly | Bhadpura | Surajpur Parauria | 403980 | Saraura | 32 | 32 | 100 | Har Gar Jal | Not Certified | 
| 3 | Bareilly | Bhadpura | Surajpur Parauria | 403981 | Kundman Banni Begam | 37 | 37 | 100 | Har Gar Jal | Not Certified | 
| 4 | Bareilly | Bhadpura | Dandia Nazmul Nisan | 403999 | Dandia Nazmul Nisan | 176 | 176 | 100 | Har Gar Jal | Not Certified |