Scheme Details
DISTRICT
Chandauli
AGENCY
ION EXCHANGE
SCHEME ID
20020027
SCHEME NAME
Lehara Khas_Bishun Purwa_Sihar WS
ESTIMATED COST
469.21
EXPENDITURE
160.11
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
10
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16679.00
Meter
Length Laid
16500.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Chandauli | Shahabganj | Lehara Khas | 475276 | Lehara Khas | 262 | 210 | 80% | Work In Progress | Not Certified |
| 2 | Chandauli | Shahabganj | Bishunpurwa | 475314 | Bishunpurwa | 180 | 150 | 83% | Work In Progress | Not Certified |
| 3 | Chandauli | Shahabganj | Sihar | 475315 | Sihar | 171 | 171 | 100% | Har Ghar Jal | Not Certified |
| 4 | Chandauli | Shahabganj | Bishunpurwa | 475316 | Salaya | 45 | 2 | 4% | Work In Progress | Not Certified |