Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Bahraich | PNC-SPML-JV | 20020322 | VIRAI GAON NAWABGANJ MVS PWS | 218.80 | 106.07 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 16 | Yes | 0 | NA | No | 4493.00 | 3500.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bahraich | Nawabganj | Virai Gaon | 441740 | Virai Gaon | 140 | 140 | 100 | Har Gar Jal | Not Certified | 
| 2 | Bahraich | Nawabganj | Virai Gaon | 441741 | Tokhaideeh | 1 | 1 | 100 | Har Gar Jal | Not Certified | 
| 3 | Bahraich | Nawabganj | Virai Gaon | 441742 | Ganeshpur Nimnhara | 148 | 148 | 100 | Har Gar Jal | Not Certified |