Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Gorakhpur NCC Ltd. 20020448 Bhainsahi Naresh, Benijot Khadahra 357.01 333.76 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
4 1 1 1 1 1 1 1 26 26 Yes 0 NA No 13085.00 12947.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Gorakhpur Brahmpur Bhainsahi Naresh 455715 Karn Majha 49 49 100 Har Gar Jal Not Certified
2 Gorakhpur Brahmpur Bhainsahi Naresh 455716 Bhainsahi Naresh 192 85 44 Work In Progress Not Certified
3 Gorakhpur Brahmpur Bhainsahi Naresh 455717 Bhainsahi Ram Datt 198 198 100 Har Gar Jal Not Certified
4 Gorakhpur Brahmpur Benijot Kharhara 455722 Benijot Khadahra 171 171 100 Har Gar Jal Not Certified