| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | NCC Ltd. | 20020516 | Kunjalgarh , Alenabad | 303.43 | 189.97 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 24 | 24 | Yes | 0 | NA | No | 15298.00 | 14678.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Campiere Ganj | Alenabad | 454651 | Alenabad | 210 | 206 | 98 | Work In Progress | Not Certified |
| 2 | Gorakhpur | Campiere Ganj | Kunjalgarh | 454653 | Kunjalgarh | 172 | 172 | 100 | Har Gar Jal | Not Certified |