Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Bareilly
AGENCY NCC Ltd.
SCHEME ID 20020547
SCHEME NAME SIRODHI ANGADPUR & ASAD NAGAR water supply scheme
ESTIMATED COST 371.41
EXPENDITURE 232.36
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 26
Procured 26 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 15138.00 Meter
Length Laid 15038.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bareilly Mirganj Asad Nagar 403210 Asad Nagar 251 249 99% Work In Progress Not Certified
2 Bareilly Mirganj Asad Nagar 403211 Kashinathpur Mustakil 166 166 100% Har Ghar Jal Not Certified
3 Bareilly Mirganj Sirodhi Angadpur 403249 Sirodhi Angadpur 346 346 100% Har Ghar Jal Not Certified