Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Bareilly | NCC Ltd. | 20020550 | THIRIA BRAHMANAN & GOOLA water supply scheme | 304.23 | 149.87 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 22 | 22 | Yes | 0 | NA | No | 11444.00 | 11420.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Mirganj | Goola | 403203 | Goola | 284 | 284 | 100 | Har Gar Jal | Not Certified | 
| 2 | Bareilly | Mirganj | Thiria Brahmanan | 403279 | Thiria Brahmanan | 106 | 106 | 100 | Har Gar Jal | Not Certified | 
| 3 | Bareilly | Mirganj | Thiria Brahmanan | 403280 | Sanjarpur | 179 | 179 | 100 | Har Gar Jal | Not Certified |