Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | NCC Ltd. | 20020553 | Neora, Harikhora | 428.75 | 268.64 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 8 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 37 | 37 | Yes | 0 | NA | No | 21721.00 | 20721.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Kauriram | Harikhora | 456411 | Harikhora | 217 | 217 | 100 | Har Gar Jal | Not Certified |
| 2 | Gorakhpur | Kauriram | Harikhora | 456412 | Musaila | 35 | 1 | 3 | Work In Progress | Not Certified |
| 3 | Gorakhpur | Kauriram | Harikhora | 456413 | Musauli | 104 | 103 | 99 | Work In Progress | Not Certified |
| 4 | Gorakhpur | Kauriram | Neora | 456417 | Neora | 112 | 111 | 99 | Work In Progress | Not Certified |
| 5 | Gorakhpur | Kauriram | Neora | 456418 | Basipar | 39 | 22 | 56 | Work In Progress | Not Certified |
| 6 | Gorakhpur | Kauriram | Neora | 456419 | Parsiya | 70 | 44 | 63 | Work In Progress | Not Certified |
| 7 | Gorakhpur | Kauriram | Neora | 456420 | Parsadeepur Urf Mishrauli | 91 | 91 | 100 | Har Gar Jal | Not Certified |
| 8 | Gorakhpur | Kauriram | Neora | 703158 | KANJRAPAR | 26 | 26 | 100 | Har Gar Jal | Not Certified |