Scheme Details
DISTRICT Bareilly
AGENCY NCC Ltd.
SCHEME ID 20020575
SCHEME NAME BARAUR water supply scheme
ESTIMATED COST 442.55
EXPENDITURE 366.66
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 29
Procured 29 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 12329.00 Meter
Length Laid 12329.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bareilly Nawabganj Baraur 403839 Baraur 968 968 100% Har Ghar Jal Not Certified