Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Gorakhpur
AGENCY NCC Ltd.
SCHEME ID 20020582
SCHEME NAME BARAIPAR
ESTIMATED COST 243.51
EXPENDITURE 232.99
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 18
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 14495.00 Meter
Length Laid 10000.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Gorakhpur Sardarnagar Varai Par 455493 Varai Par 184 177 96% Work In Progress Not Certified
2 Gorakhpur Sardarnagar Varai Par 455494 Palia 95 94 99% Work In Progress Not Certified
3 Gorakhpur Sardarnagar Varai Par 455495 Tilauli 151 144 95% Work In Progress Not Certified