DISTRICT Lucknow
AGENCY NCC Ltd.
SCHEME ID 20020713
SCHEME NAME Naibasti Bhithaura
ESTIMATED COST 256.57
EXPENDITURE 169.61
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 18
Procured 18 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 8670.00 Meter
Length Laid 8670.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Lucknow Mal Naibasti Bhithaura 415400 Naibasti Bhithaura 396 392 99% Work In Progress Not Certified