Scheme Details
DISTRICT
Jaunpur
AGENCY
Welspun Kaveri Infraprojects JV
SCHEME ID
20020911
SCHEME NAME
Husainpur
ESTIMATED COST
330.17
EXPENDITURE
129.59
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18121.00
Meter
Length Laid
18121.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Ramnagar | Husainpur | 470714 | Husainpur | 264 | 264 | 100% | Har Ghar Jal | Not Certified |
| 2 | Jaunpur | Ramnagar | Husainpur | 470715 | Nindurpur | 106 | 105 | 99% | Work In Progress | Not Certified |
| 3 | Jaunpur | Ramnagar | Husainpur | 470716 | Manapur | 78 | 78 | 100% | Har Ghar Jal | Not Certified |