Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Jaunpur
AGENCY Welspun Kaveri Infraprojects JV
SCHEME ID 20020925
SCHEME NAME Aunra
ESTIMATED COST 426.13
EXPENDITURE 69.33
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 44
Procured 44 KW
Work Status No
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 21301.00 Meter
Length Laid 21020.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Jaunpur Ramnagar Aunra 470811 Aunra 769 769 100% Har Ghar Jal Not Certified