Scheme Details
DISTRICT
Mau
AGENCY
LC INFRA
SCHEME ID
20020978
SCHEME NAME
PIJARA WATER SUPPLY SCHEME
ESTIMATED COST
686.35
EXPENDITURE
499.81
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
50
Procured
50
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
27588.00
Meter
Length Laid
25650.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Pardaha | Pijara | 465625 | Pijara | 674 | 674 | 100% | Har Ghar Jal | Not Certified |
| 2 | Mau | Pardaha | Pijara | 465626 | Luduhi | 132 | 132 | 100% | Har Ghar Jal | Not Certified |
| 3 | Mau | Pardaha | Pijara | 465627 | Alipur | 148 | 143 | 97% | Work In Progress | Not Certified |