Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Kanpur Nagar | Vindhya-GAJA (JV) | 20021031 | Akbarpur jhawaiya & Agapur Multivillage scheme | 440.47 | 331.95 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 44 | 44 | Yes | 0 | NA | No | 18815.00 | 17128.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kanpur Nagar | Patara | Agapur | 422544 | Agapur | 286 | 37 | 13 | Work In Progress | Not Certified | 
| 2 | Kanpur Nagar | Patara | Akbarpur Jhawaiya | 422552 | Akbarpur Jhawaiya | 603 | 361 | 60 | Work In Progress | Not Certified |