Scheme Details
DISTRICT
Mau
AGENCY
LC INFRA
SCHEME ID
20021120
SCHEME NAME
NASIRABAD KALA WATER SUPPLY SCHEME
ESTIMATED COST
400.64
EXPENDITURE
226.77
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
24221.00
Meter
Length Laid
24220.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Ratanpura | Nasirabad Kala | 465855 | Nasirabad Kala | 1019 | 995 | 98% | Work In Progress | Not Certified |
| 2 | Mau | Ratanpura | Nasirabad Kala | 465856 | Dalpatpur | 9 | 8 | 89% | Work In Progress | Not Certified |