Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Welspun Kaveri Infraprojects JV | 20021185 | Pachewara | 385.61 | 145.40 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 18 | 18 | No | 0 | NA | No | 20927.00 | 20927.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Karanjakala | Parapatti | 470358 | Parapatti | 178 | 157 | 88 | Work In Progress | Not Certified | 
| 2 | Jaunpur | Karanjakala | Parapatti | 470359 | Dharmasari | 118 | 93 | 79 | Work In Progress | Not Certified | 
| 3 | Jaunpur | Karanjakala | Pachewara | 470366 | Pachewara | 156 | 140 | 90 | Work In Progress | Not Certified | 
| 4 | Jaunpur | Karanjakala | Pachewara | 470367 | Bhirapur | 61 | 61 | 100 | Har Gar Jal | Not Certified | 
| 5 | Jaunpur | Karanjakala | Pachewara | 470368 | Shekhawalia | 66 | 66 | 100 | Har Gar Jal | Not Certified |