Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Kaushambi
AGENCY JMC - Lakshmi (JV)
SCHEME ID 20021447
SCHEME NAME Chikwa Reorganisation water supply scheme
ESTIMATED COST 1989.73
EXPENDITURE 1278.09
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 8
T/W Progress
Required 8
Boring Done 8
Air Compressor Done 8
O.P. Unit Done 8
OHT Progress
Required 3
Work Started 3
Work Completed 3
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 112
Transformer Procured NA
Work Status No
Distribution Line
Total Length 62616.00 Meter
Length Laid 60902.00 Meter

Scheme Assigned Villages

8 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Kaushambi Kaushambi Bhakanda 431328 Jamalpur Bhakanda 97 86 89% Work In Progress Not Certified
2 Kaushambi Kaushambi Bhakanda 431329 Bhakanda Uparhar 611 611 100% Har Ghar Jal Not Certified
3 Kaushambi Kaushambi Mahila 431365 Mahila Uparhar 346 346 100% Har Ghar Jal Certified
4 Kaushambi Kaushambi Aingawa Uparhar 431366 Dhana Uparhar 280 280 100% Har Ghar Jal Certified
5 Kaushambi Kaushambi Aingawa Uparhar 431367 Aingawa Uparhar 396 396 100% Har Ghar Jal Certified
6 Kaushambi Kaushambi Chhekawa 431368 Chhekawa Uparhar 599 599 100% Har Ghar Jal Not Certified
7 Kaushambi Kaushambi Diya Uparhar 431369 Diya Uparhar 602 591 98% Work In Progress Not Certified
8 Kaushambi Kaushambi Dharampur 431370 Dharampur 573 571 100% Work In Progress Not Certified