Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Siddharth Nagar VSA 20021570 JUA RAI WSS 155.15 125.31 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 0 13 13 Yes 0 NA No 4649.00 4649.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Siddharth Nagar Bhanwapur Jua Rai 447927 Khamharia 69 58 84 Work In Progress Not Certified
2 Siddharth Nagar Bhanwapur Jua Rai 447928 Jua Rai 95 84 88 Work In Progress Not Certified