Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | VSA | 20021600 | ATHKONIYA & BAGAHAWA WSS | 303.95 | 157.32 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 11327.00 | 11327.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Shohratgarh | Bagahawa | 446499 | Bagahawa | 164 | 164 | 100 | Har Gar Jal | Not Certified | 
| 2 | Siddharth Nagar | Shohratgarh | Bagahawa | 446500 | Madhawapur | 116 | 110 | 95 | Work In Progress | Not Certified | 
| 3 | Siddharth Nagar | Shohratgarh | Athkoniya | 446505 | Atha Koniya | 182 | 180 | 99 | Work In Progress | Not Certified |