Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20021846 | Jalalpur Asra & Harganpur Gram Panchayat Water Supply | 331.51 | 178.82 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 8556.00 | 8515.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Netaur | Jalalpur Asra | 386954 | Jalalpur Asra | 128 | 128 | 100 | Har Gar Jal | Not Certified |
| 2 | Bijnor | Netaur | Jalalpur Asra | 386958 | Shadipur | 120 | 120 | 100 | Har Gar Jal | Not Certified |
| 3 | Bijnor | Netaur | Jalalpur Asra | 386959 | Ismailpur | 57 | 57 | 100 | Har Gar Jal | Not Certified |
| 4 | Bijnor | Netaur | Harganpur | 386961 | Harganpur | 203 | 203 | 100 | Har Gar Jal | Not Certified |
| 5 | Bijnor | Netaur | Harganpur | 386962 | Muzahidpur | 90 | 90 | 100 | Har Gar Jal | Not Certified |