Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Lucknow | NCC Ltd. | 20021949 | Kolava Bhanaura & Adampur | 371.75 | 227.15 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 25 | 25 | Yes | 0 | NA | No | 13969.00 | 13969.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lucknow | Mal | Kolava Bhanaura | 415379 | Kolava Bhanaura | 411 | 390 | 95 | Work In Progress | Not Certified | 
| 2 | Lucknow | Mal | Adampur | 415380 | Khakhara | 95 | 76 | 80 | Work In Progress | Not Certified | 
| 3 | Lucknow | Mal | Adampur | 415381 | Adampur | 150 | 146 | 97 | Work In Progress | Not Certified |