Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Lucknow
AGENCY NCC Ltd.
SCHEME ID 20022016
SCHEME NAME Fatehnagar
ESTIMATED COST 251.75
EXPENDITURE 202.31
AUTOMATION STATUS Not Integrated
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 18
Procured 18 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 9053.00 Meter
Length Laid 9101.00 Meter

Scheme Assigned Villages

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Lucknow Malihabad Fatehnagar 415495 Fatehnagar 223 220 99% Work In Progress Not Certified
2 Lucknow Malihabad Fatehnagar 415496 Shivdaspur 140 125 89% Work In Progress Not Certified