Scheme Details
DISTRICT
Ayodhya
AGENCY
VSA
SCHEME ID
20022227
SCHEME NAME
GOVINDPUR WSS
ESTIMATED COST
334.80
EXPENDITURE
308.02
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
18
Procured
18
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
2404.60
Meter
Length Laid
19038.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Bikapur | Govindpur | 437223 | Govindpur | 62 | 62 | 100% | Har Ghar Jal | Not Certified |
| 2 | Ayodhya | Bikapur | Govindpur | 437224 | Pure Pur Bachana | 81 | 81 | 100% | Har Ghar Jal | Not Certified |
| 3 | Ayodhya | Bikapur | Govindpur | 437225 | Bhavnth Pur | 25 | 25 | 100% | Har Ghar Jal | Not Certified |
| 4 | Ayodhya | Bikapur | Govindpur | 437226 | Pranpur | 73 | 73 | 100% | Har Ghar Jal | Not Certified |
| 5 | Ayodhya | Bikapur | Govindpur | 437227 | Kilahana | 55 | 55 | 100% | Har Ghar Jal | Not Certified |
| 6 | Ayodhya | Bikapur | Govindpur | 437232 | SAHA PARA | 114 | 114 | 100% | Har Ghar Jal | Not Certified |