Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Bulandshahr
AGENCY Power Mech Projects Ltd
SCHEME ID 20022802
SCHEME NAME Kanakpur Alias Talabpur
ESTIMATED COST 345.84
EXPENDITURE 308.86
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 27
Procured 27 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 11925.00 Meter
Length Laid 11900.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bulandshahr Sikandrabad Kanakpur Alias Taliwpur 393176 Kanakpur Alias Taliwpur 395 395 100% Har Ghar Jal Certified
2 Bulandshahr Sikandrabad Kanakpur Alias Taliwpur 393177 Nagla Barodah 170 170 100% Har Ghar Jal Certified