Scheme Details
DISTRICT
Sambhal
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20023109
SCHEME NAME
HARIPUR MILAK WATER SUPPLY SCHEME
ESTIMATED COST
206.13
EXPENDITURE
164.17
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
4712.00
Meter
Length Laid
5269.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sambhal | Asmoli | Haripur Milak | 388830 | Haripur Milak | 290 | 290 | 100% | Har Ghar Jal | Not Certified |
| 2 | Sambhal | Asmoli | Haripur Milak | 388831 | Nehrola | 92 | 92 | 100% | Har Ghar Jal | Not Certified |