Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Farrukhabad | GVPR | 20023288 | Paharpur Majra Atseni W/S Scheme | 238.29 | 174.66 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 7813.00 | 7107.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Farrukhabad | Nawabganj | Paharpur Majra Atseni | 418110 | Paharpur Majra Atseni | 106 | 97 | 92 | Work In Progress | Not Certified | 
| 2 | Farrukhabad | Nawabganj | Paharpur Majra Atseni | 655886 | ATHASENI | 159 | 159 | 100 | Har Gar Jal | Not Certified |