Scheme Details
DISTRICT
Sant Kabeer Nagar
AGENCY
Megha
SCHEME ID
20023401
SCHEME NAME
BHAGVANPUR
ESTIMATED COST
286.78
EXPENDITURE
166.38
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
15041.00
Meter
Length Laid
12845.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | Baghauli | Bhagvanpur | 452140 | Bhagvan Pur | 504 | 504 | 100% | Har Ghar Jal | Not Certified |