Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Chandauli | GA INFRA - BABA (JV) | 20023579 | Garhwa_Bhagupur WS | 449.56 | 248.48 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 30 | 30 | Yes | 0 | NA | No | 19742.00 | 17499.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Chandauli | Chakiya | Garhwa | 475091 | Garhwa | 280 | 280 | 100 | Har Gar Jal | Not Certified |
| 2 | Chandauli | Chakiya | Garhwa | 475092 | Pipra Kalan | 122 | 122 | 100 | Har Gar Jal | Not Certified |
| 3 | Chandauli | Chakiya | Bhagupur | 475097 | Bhagupur | 269 | 269 | 100 | Har Gar Jal | Not Certified |
| 4 | Chandauli | Chakiya | Bhagupur | 475098 | Rampur Chamrahi | 207 | 207 | 100 | Har Gar Jal | Not Certified |