Scheme Details
DISTRICT Pratapgarh
AGENCY Power Mech Projects Ltd
SCHEME ID 20023643
SCHEME NAME KANYAEYADULLAPUR & HARNAHAR GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST 358.41
EXPENDITURE 219.49
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 27
Procured 27 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 21585.00 Meter
Length Laid 21585.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Pratapgarh Rampur Sangramgarh Hernahar 428937 Hernahar 300 294 98% Work In Progress Not Certified
2 Pratapgarh Rampur Sangramgarh Kanhaiya Dullapur 428938 Kanhaiya Dullapur 124 124 100% Har Ghar Jal Not Certified
3 Pratapgarh Rampur Sangramgarh Kanhaiya Dullapur 428939 Tenda 157 157 100% Har Ghar Jal Not Certified