Scheme Details
DISTRICT
Jaunpur
AGENCY
Welspun Kaveri Infraprojects JV
SCHEME ID
20023703
SCHEME NAME
Jiyanpur
ESTIMATED COST
543.76
EXPENDITURE
259.18
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
44
Procured
44
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
21728.00
Meter
Length Laid
21728.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Mariyahun | Mukundpur | 469837 | Mukundpur | 334 | 331 | 99% | Work In Progress | Not Certified |
| 2 | Jaunpur | Mariyahun | Jiyanpur | 469838 | Raghunathpur | 33 | 33 | 100% | Har Ghar Jal | Not Certified |
| 3 | Jaunpur | Mariyahun | Jiyanpur | 469839 | Jiyanpur | 113 | 111 | 98% | Work In Progress | Not Certified |
| 4 | Jaunpur | Mariyahun | Jiyanpur | 469840 | Kolhara | 30 | 30 | 100% | Har Ghar Jal | Not Certified |
| 5 | Jaunpur | Mariyahun | Jiyanpur | 469841 | Jiyaramau | 111 | 111 | 100% | Har Ghar Jal | Not Certified |
| 6 | Jaunpur | Mariyahun | Jiyanpur | 469842 | Uday Raj Patti | 5 | 4 | 80% | Work In Progress | Not Certified |