Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Chandauli
AGENCY VSA
SCHEME ID 20023734
SCHEME NAME Pachokhar WS
ESTIMATED COST 487.21
EXPENDITURE 188.53
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 28
Procured 28 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 14661.00 Meter
Length Laid 14661.00 Meter

Scheme Assigned Villages

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Chandauli Niyamatabad Pachokhar 474669 Pachokhar 743 743 100% Har Ghar Jal Not Certified
2 Chandauli Niyamatabad Pachokhar 474670 Takiya 80 80 100% Har Ghar Jal Not Certified