| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Moradabad | NKG-PRIMUS (JV) | 20023822 | ABHANPUR NARauli village water supply scheme | 294.29 | 110.80 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 23 | 23 | Yes | 0 | NA | No | 9884.00 | 9508.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Bilari | Abhanpur Narauli | 388646 | Abhanpur Narauli | 194 | 184 | 95 | Work In Progress | Not Certified |
| 2 | Moradabad | Bilari | Abhanpur Narauli | 388647 | Kua Khera | 227 | 185 | 81 | Work In Progress | Not Certified |
| 3 | Moradabad | Bilari | Abhanpur Narauli | 388648 | Jwala Puri | 124 | 115 | 93 | Work In Progress | Not Certified |