Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20023882 | Kanakpur Gram Panchayat Water Supply | 249.29 | 193.69 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 4911.00 | 4269.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Kotwali | KANAKPUR | 386644 | Kanakpur | 94 | 90 | 96 | Work In Progress | Not Certified | 
| 2 | Bijnor | Kotwali | KANAKPUR | 386645 | Disondi Wala Desh | 93 | 69 | 74 | Work In Progress | Not Certified | 
| 3 | Bijnor | Kotwali | KANAKPUR | 386646 | Nagala Dadda | 113 | 103 | 91 | Work In Progress | Not Certified | 
| 4 | Bijnor | Kotwali | KANAKPUR | 386647 | Abdullapur Khalsa | 4 | 1 | 25 | Work In Progress | Not Certified | 
| 5 | Bijnor | Kotwali | KANAKPUR | 386648 | Rampur Asaf | 22 | 1 | 5 | Work In Progress | Not Certified |