DISTRICT Sant Ravidas Nagar
AGENCY Welspun Kaveri Infraprojects JV
SCHEME ID 20024084
SCHEME NAME Gori Multi Village Water Supply Scheme
ESTIMATED COST 336.88
EXPENDITURE 203.79
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 27
Procured 27 KW
Work Status No
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 9688.00 Meter
Length Laid 9688.00 Meter

Scheme Assigned Villages

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sant Ravidas Nagar Aurai GORI DEEH 477270 GAURI 425 425 100% Har Ghar Jal Not Certified
2 Sant Ravidas Nagar Aurai GORI DEEH 477271 AHARPUR 138 97 70% Work In Progress Not Certified
3 Sant Ravidas Nagar Aurai GORI DEEH 477272 DARAVPUR 34 34 100% Har Ghar Jal Not Certified