Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Budaun
AGENCY PNC-SPML-JV
SCHEME ID 20024210
SCHEME NAME SADULLAPUR BHITARA
ESTIMATED COST 168.48
EXPENDITURE 98.61
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 13
Procured 13 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 3130.00 Meter
Length Laid 3130.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Budaun Salarpur Sadullapur Bhitara 401891 Sadullapur Bhitara 410 410 100% Har Ghar Jal Certified