Scheme Details
DISTRICT
Bijnor
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20024241
SCHEME NAME
Ibrahimpur Sadho Gram Panchayat Water Supply
ESTIMATED COST
227.66
EXPENDITURE
155.01
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
5821.00
Meter
Length Laid
5438.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Netaur | Ibrahimpur Sadho | 386830 | Ibrahimpur Sadho | 264 | 264 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bijnor | Netaur | Ibrahimpur Sadho | 386831 | Dhakola | 104 | 90 | 87% | Work In Progress | Not Certified |