Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Kanpur Nagar | Vindhya-GAJA (JV) | 20024254 | BARADHARI & BABIBHITARA GRAM PANCHAYAT WATER SUPPLY SCHEME- MULTI VILLAGE | 359.62 | 270.80 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 37 | 37 | Yes | 0 | NA | No | 11782.00 | 10909.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kanpur Nagar | Sarsaul | Babibhitari | 422415 | Babibhitari | 349 | 346 | 99 | Work In Progress | Not Certified | 
| 2 | Kanpur Nagar | Sarsaul | Babibhitari | 422416 | Babi Chingi | 47 | 42 | 89 | Work In Progress | Not Certified | 
| 3 | Kanpur Nagar | Sarsaul | Baradhari | 422431 | Baradhari | 323 | 312 | 97 | Work In Progress | Not Certified |