Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20024259 | MUSTAFABAD GP WSS | 198.86 | 139.82 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 17 | 17 | Yes | 0 | NA | No | 13084.00 | 12499.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Saltaua Gopal Pur | Mustafabad | 448887 | Mustafabad | 130 | 130 | 100 | Har Gar Jal | Certified | 
| 2 | Basti | Saltaua Gopal Pur | Mustafabad | 448888 | Bichhiya Asare | 7 | 7 | 100 | Har Gar Jal | Certified | 
| 3 | Basti | Saltaua Gopal Pur | Mustafabad | 448889 | Bichhiya Ganj | 65 | 65 | 100 | Har Gar Jal | Certified | 
| 4 | Basti | Saltaua Gopal Pur | Mustafabad | 448890 | Pokhar Bhitwa | 128 | 128 | 100 | Har Gar Jal | Certified |