Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20024335 | Basera Gram Panchayat Water Supply | 286.08 | 217.09 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 8076.00 | 8752.40 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Kiratpur | Basera | 385883 | Basera | 220 | 220 | 100 | Har Gar Jal | Not Certified |
| 2 | Bijnor | Kiratpur | Basera | 385884 | Hamidpur Makhan | 113 | 107 | 95 | Work In Progress | Not Certified |
| 3 | Bijnor | Kiratpur | Basera | 385885 | Nasirpur Mithari | 45 | 45 | 100 | Har Gar Jal | Not Certified |