Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20024421 | BARDIYA LOHAR | 485.12 | 191.84 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 31 | 31 | Yes | 0 | NA | No | 36098.00 | 35380.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Dubaulia | Bardiya Lohar | 450162 | Bardiya Lohar | 175 | 174 | 99 | Work In Progress | Not Certified |
| 2 | Basti | Dubaulia | Bardiya Lohar | 450163 | Majha Akhanpur | 94 | 93 | 99 | Work In Progress | Not Certified |
| 3 | Basti | Dubaulia | Bardiya Lohar | 450164 | Akhanpur | 148 | 147 | 99 | Work In Progress | Not Certified |
| 4 | Basti | Dubaulia | Bardiya Lohar | 450165 | Malikpur | 112 | 110 | 98 | Work In Progress | Not Certified |
| 5 | Basti | Dubaulia | Bardiya Lohar | 450166 | Bhuwaria | 130 | 129 | 99 | Work In Progress | Not Certified |