Scheme Details
DISTRICT
Prayagraj
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20024430
SCHEME NAME
THULAMA MULTI VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST
332.15
EXPENDITURE
163.04
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
28
Procured
28
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17841.00
Meter
Length Laid
17841.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Saidabad | Thulama | 433558 | Thulama | 209 | 209 | 100% | Har Ghar Jal | Not Certified |
| 2 | Prayagraj | Saidabad | Thulama | 433559 | Dhankeshra | 130 | 130 | 100% | Har Ghar Jal | Not Certified |
| 3 | Prayagraj | Saidabad | Bizhawaniya | 433588 | Bizhawaniya | 273 | 259 | 95% | Work In Progress | Not Certified |