Scheme Details
DISTRICT Etawah
AGENCY Indian Hume Pipe
SCHEME ID 20024510
SCHEME NAME BHULPUR PWS
ESTIMATED COST 156.54
EXPENDITURE 139.19
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 13
Procured 13 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 4141.00 Meter
Length Laid 4242.90 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Etawah Mahewa Bholpur 420048 Bhulpur 188 188 100% Har Ghar Jal Not Certified
2 Etawah Mahewa Bholpur 420049 Mubarikpur 151 151 100% Har Ghar Jal Not Certified